PSM Structures provided structural engineering and detailing support for the Power Station block of Tata Electronics’ semiconductor fabrication facility (DF1), one of India’s most advanced industrial infrastructure projects. This facility required precise, code-compliant RCC and precast design integration to ensure safety, serviceability, and speed during construction.
Scope of Work
- RCC structural design for the entire Power Station block (Building L03)
- Framing layout, column grid optimization, and structural system finalization
- Design validation for key service areas, including electrical and utility zones
- Coordination with architectural and MEP teams for smooth interface detailing
- GFC drawings prepared for foundations, slabs, columns, beams, and roofs
Key Highlights
- Structural System: RCC Frame with service integration zones
- Design Tools Used: STAAD Pro, AutoCAD, Excel-based custom calculators
- Project Type: High-performance industrial facility
"PSM Structures delivered precise and coordinated designs under a tight schedule. Their clarity in RCC detailing made execution straightforward on site."
Project Lead, Tata
Challenges Addressed
- Structural design aligned with heavy MEP service requirements
- Tight coordination across architectural, civil, and electrical disciplines
- Fast-tracked GFC delivery schedule due to the client’s strict timeline
Outcome
Delivered precise, buildable drawings ahead of schedule with full compliance to IS codes and Tata’s internal design protocols. The Power Station block’s structural design helped streamline the integration of power infrastructure within the DF1 Fab, contributing to India’s growing semiconductor ecosystem.